Update of URBAN-67A on

Update of URBAN-67A on

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7,8,9,10,11,12

Plinth Work 

100%

2

11,12

Super Structure

99%

3

9,10

Super Structure

99%

4

6

Super Structure

99%

5

7,8

Super Structure

99%

6

5

Super Structure

99%

7

4

Super Structure

99%

8

1,3

Super Structure

99%

9

2

Structure

56%

10

Commercial

Structure

40%

11

12

Finishing Work

55%

12

11

Finishing Work 

50%

13

9,10

Finishing Work

10%

14

8

Finishing Work 

6%

15

7

Finishing Work 

6%

16

6

Finishing Work 

10%

17

5

Finishing Work

10%

18

4

Finishing Work

8%

19

3

Finishing Work 

6%

20

1,2,3,4,5,6,6,7,8,9,10,11,12

External Development

15%

 