Sr.No
|
Towers
|
Work Description
|
Progress
|
1
|
1,2,3,4,5,6,7,UGT, STP, AGANWADI, ESS, VCB ROOM, COMMERCIAL - 1, COMMERCIAL - 2, METER ROOM & VCB ROOM, GUARD ROOM
|
Sub Structure Work
|
100%
|
2
|
INTERNAL ROAD
|
Sub Structure Work
|
40%
|
3
|
1,2,3,4,5,6,7, STP, UGT, AGANWADI, VCB ROOM, ESS
|
Super Structure Work
|
100%
|
4
|
COMMERCIAL
|
Super Structure Work
|
90%
|
5
|
INTERNAL ROAD
|
Super Structure Work
|
40%
|
6
|
GUARD ROOM
|
Super Structure Work
|
50%
|
7
|
1
|
Finishing Work
|
80% (Tile work - 80%, Putty Work - 90%, Internal Primer Work-0%, External Primer-50%)
|
8
|
2
|
Finishing Work
|
85%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-90%)
|
9
|
3
|
Finishing Work
|
85%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-90%)
|
10
|
4
|
Finishing Work
|
85%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-90%)
|
11
|
5
|
Finishing Work
|
85%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-90%)
|
12
|
6
|
Finishing Work
|
85%(Tile work - 100%, Putty Work - 90%, External Primer-90%)
|
13
|
7
|
Finishing Work
|
70%(Tile work - 80%, Putty Work - 60%)
|
14
|
STP
|
Finishing Work
|
90%(Internal Primer Work-100%)
|
15
|
UGT
|
Finishing Work
|
90%(Internal Primer Work-100%)
|
16
|
AGANWADI
|
Finishing Work
|
80%
|
17
|
COMMERCIAL
|
Finishing Work
|
50%(Granite work- 10%)
|
18
|
VCB ROOM
|
Finishing Work
|
0%
|
19
|
ESS
|
Finishing Work
|
(Internal Primer Work-100%, External Primer-100%)
|
20
|
INTERNAL ROAD
|
Finishing Work
|
0%
|
21
|
GUARD ROOM
|
Finishing Work
|
0%
|