Sr.No
|
Towers
|
Work Description
|
Progress
|
1
|
1,2,3,4,5,6,7,UGT, STP, AGANWADI, ESS, VCB ROOM, COMMERCIAL - 1, COMMERCIAL - 2, METER ROOM & VCB ROOM, GUARD ROOM
|
Sub Structure Work
|
100%
|
2
|
1,2,3,4,5,6,7, STP, UGT, AGANWADI, VCB ROOM, ESS, COMMERCIAL, INTERNAL ROAD
|
Super Structure Work
|
100%
|
3
|
GUARD ROOM
|
Super Structure Work
|
50%
|
4
|
1
|
Finishing Work
|
85% (Tile work - 93%, Putty Work - 90%, Internal Primer Work-50%, External Primer-95%)
|
5
|
2
|
Finishing Work
|
90%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-90%, External Primer-95%)
|
6
|
3
|
Finishing Work
|
90%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-95%)
|
7
|
4
|
Finishing Work
|
90%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-0%, External Primer-95%)
|
8
|
5
|
Finishing Work
|
90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-20%, External Primer-95%)
|
9
|
6
|
Finishing Work
|
90%(Tile work - 100%, Putty Work - 100%, Internal Primer- 0%, External Primer-95%)
|
10
|
7
|
Finishing Work
|
90%(Tile work - 100%, Putty Work - 100% , Internal primer- 0%, External primer 95%)
|
11
|
STP
|
Finishing Work
|
95%(Internal Primer Work-100%)
|
12
|
UGT
|
Finishing Work
|
95%(Internal Primer Work-100%)
|
13
|
AGANWADI
|
Finishing Work
|
100%(Flooring-100%, glazing 100%)
|
14
|
COMMERCIAL
|
Finishing Work
|
80%(Granite work- 85%, Glazing work- 60%, Aluminum louver work and false ceiling 0%)
|
15
|
VCB ROOM
|
Finishing Work
|
90%
|
16
|
ESS
|
Finishing Work
|
100%(Internal Primer Work-100%, External Primer-100%)
|
17
|
INTERNAL ROAD
|
Finishing Work
|
100%(DBM complete)
|
18
|
GUARD ROOM
|
Finishing Work
|
50%(Granite work-95%,)
|