Pyramid Imperial Estate Sector 70A

Pyramid Imperial Estate Sector 70A

Sr.No

 

Work Description

Progress 

1

 

Main Entrance Gate Work

5% (Foundation for Boom Barrier completed)

2

 

Sewer Line Work 

100%

3

 

Storm Water Work

100%

4

 

Rainwater Harvesting Work 

100%

5

 

Sewarage Treatment Plant Work 

90%

6

 

Under Ground Water Tank Work 

95%

7

 

Water Supply Work 

100%

8

 

Road Work 

95%

9

 

Electrical Sub-station Work 

100%

10

 

Laying of Cables Work 

100%

11

 

External Developments, Street Lights, Landscaping Work 

95%

 