PYRAMID HEIGHTS- SECTOR-85

PYRAMID HEIGHTS- SECTOR-85

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, COMMERCIAL-2, MEATER ROOM & VCB ROOM, GUARD ROOM 

Sub Structure Work 

100%

2

1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-A, COMMERCIAL-B, COMMERCIAL-C, AGANWADI

Sub Structure Work  

100%

3

1

Finishing Work 

90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%,External Paint-80%)

4

2

Finishing Work 

90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%,External Paint-80%)

5

3

Finishing Work 

90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%,External Paint-80%)

6

4

Finishing Work 

90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%,External Paint-80%)

7

5

Finishing Work 

85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%,External Paint-80%)

8

6

Finishing Work

85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%,External Paint-80%)

9

7

Finishing Work 

70%(Tile work - 100%, Putty Work - 70%, Internal Primer Work-0%, External Primer-50%, Texture-0%)

10

STP

Finishing Work 

100%

11

UGT

Finishing Work 

100%

12

AGANWADI

Finishing Work

95%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, External Paint 80%)

13

COMMERCIAL - A

Finishing Work 

80%

14

COMMERCIAL - B

Finishing Work

85%

15

COMMERCIAL - C

Finishing Work

95%

16

VCB ROOM

Finishing Work

80%

17

ESS

Finishing Work

80%

18

INTERNAL ROAD

Finishing Work

80%(GSB 1st Layer 100%, 2nd Layer 100%, DBM 90%)

19

GUARD ROOM 

Finishing Work

0%

 