PYRAMID HEIGHTS- SECTOR-85

PYRAMID HEIGHTS- SECTOR-85

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, COMMERCIAL-2, MEATER ROOM & VCB ROOM

Sub Structure Work 

100%

2

GUARD ROOM 

Sub Structure Work 

60%

3

1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-A, COMMERCIAL-B, COMMERCIAL-C, AGANWADI

Sub Structure Work  

100%

4

1

Finishing Work 

85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%)

5

2

Finishing Work 

85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%)

6

3

Finishing Work 

85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%)

7

4

Finishing Work 

85%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%, Texture-100%)

8

5

Finishing Work 

80%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-0%, External Primer-100%, Texture-100%)

9

6

Finishing Work

80%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-0%, External Primer-100%, Texture-100%)

10

7

Finishing Work 

30%(Tile work - 30%, Putty Work - 60%, Internal Primer Work-0%, External Primer-50%, Texture-0%)

11

STP

Finishing Work 

100%

12

UGT

Finishing Work 

100%

13

AGANWADI

Finishing Work

90%(Tile work - 100%, Putty Work - 100%, Internal Primer Work-100%, External Primer-100%)

14

COMMERCIAL - A

Finishing Work 

70%

15

COMMERCIAL - B

Finishing Work

60%

16

COMMERCIAL - C

Finishing Work

90%

17

VCB ROOM

Finishing Work

80%

18

ESS

Finishing Work

80%

19

INTERNAL ROAD

Finishing Work

60%(GSB 1st Layer 85%, 2nd Layer 30%)

20

GUARD ROOM 

Finishing Work

0%

 