PYRAMID HEIGHTS- SECTOR-85

PYRAMID HEIGHTS- SECTOR-85

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7 UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, COMMERCIAL-2, MEATER ROOM & VCB ROOM

Sub Structure Work 

100%

2

1,2,3,4,5,6,7 STP, UGT, COMMERCIAL-1, COMMERCIAL-2, VCB ROOM,  ESS

Super Structure Work 

100%

3

1

Finishing Work 

Tile work - 100%, Putty Work - 80%, Internal Primer Work-70%, External Primer-70%

4

2

Finishing Work 

Tile work - 100%, Putty Work - 80%, Internal Primer Work-70%, External Primer-70%

5

3

Finishing Work 

Tile work - 100%, Putty Work - 80%, Internal Primer Work-70%, External Primer-70%

6

4

Finishing Work 

Tile work - 100%, Putty Work - 80%, Internal Primer Work-70%, External Primer-70%

7

5

Finishing Work 

Tile work - 100%, Putty Work - 80%, Internal Primer Work-00%, External Primer-70%

8

6

Finishing Work 

Tile work - 100%, Putty Work - 80%, Internal Primer Work-00%

9

7

Finishing Work

Yet to be started

10

STP

Finishing Work 

95%

11

UGT

Finishing Work 

95%

12

COMMERCIAL -1

Finishing Work 

Started

13

COMMERCIAL -2

Finishing Work

Started

14

VCB ROOM

Finishing Work 

100%

15

ESS

Finishing Work

100%

 