Sr.No
|
Towers
|
Work Description
|
Progress
|
1
|
1,2,3,4,5,6, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, COMMERCIAL-2, MEATER ROOM & VCB ROOM
|
Sub Structure Work
|
100%
|
2
|
1,2,3,4,5,6, STP, UGT, COMMERCIAL-1, COMMERCIAL-2, VCB ROOM,
|
Super Structure Work
|
100%
|
3
|
7
|
Super Structure Work
|
90% (Only Mumty, Machine room balance)
|
4
|
ESS
|
Super Structure Work
|
80%
|
5
|
1
|
Finishing Work
|
Tile work - 95%, Putty Work - 60%
|
6
|
2
|
Finishing Work
|
Tile work - 95%, Putty Work - 60%
|
7
|
3
|
Finishing Work
|
Tile work - 95%, Putty Work - 60%
|
8
|
4
|
Finishing Work
|
Tile work - 95%, Putty Work - 60%
|
9
|
5
|
Finishing Work
|
Tile work - 90%, Putty Work - 60%
|
10
|
6
|
Finishing Work
|
Tile work - 90%, Putty Work - 60%
|
11
|
7
|
Finishing Work
|
Yet to be started
|
12
|
STP
|
Finishing Work
|
90%
|
13
|
UGT
|
Finishing Work
|
90%
|
14
|
COMMERCIAL -1
|
Finishing Work
|
Started
|
15
|
COMMERCIAL -2
|
Finishing Work
|
Started
|
16
|
VCB ROOM
|
Finishing Work
|
100%
|
17
|
ESS
|
Finishing Work
|
Started
|