Pyramid Elite Sector-86

Pyramid Elite Sector-86

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM

Sub Structure Work

100%

2

AGANWADI, INTERNAL ROAD, GUARD ROOM  

 

100%

3

1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1,  VCB ROOM, AGANWADI, INTERNAL ROAD, GUARD ROOM 

Super Structure Work 

100%

4

1

Finishing Work 

98% (Tile work - 100%, Putty Work - 98%, Internal Primer Work-90%, External Primer-100%)

5

2

Finishing Work 

95% (Tile work - 100%, Putty Work - 95%, Internal Primer Work-35%, External Primer-100%)

6

3

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%)

7

4

Finishing Work 

98% (Tile work - 100%, Putty Work - 98%, Internal Primer Work-90%, External Primer-100%)

8

5

Finishing Work 

98% (Tile work - 100%, Putty Work - 98%, Internal Primer Work-90%, External Primer-100%)

9

6

Finishing Work 

98% (Tile work - 100%, Putty Work - 98%, Internal Primer Work-90%, External Primer-100%)

10

7

Finishing Work 

98% (Tile work - 100%, Putty Work - 98%, Internal Primer Work-90%, External Primer-100%)

11

STP 

Finishing Work  

100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 100%)

12

UGT

Finishing Work 

100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 100%)

13

AGANWADI

Finishing Work  

95%(Tile work - 100%, Putty Work - 90%, Internal Primer Work-90%, External Primer-100%)

14

COMMERCIAL - 1

Finishing Work  

90% (Tile work - 100%, Putty work - 95%, External Primer 95%)

15

VCB ROOM

Finishing Work  

100% (Flooring Work - 100%, Putty Work - 100%, External Primer - 100%)

16

ESS

Finishing Work  

100% (Flooring Work - 100%, Putty Work - 100%, External Primer - 100%)

17

INTERNAL ROAD

Finishing Work  

90%

18

GUARD ROOM 

Finishing Work  

90%

 

 