Pyramid Elite Sector-86

Pyramid Elite Sector-86

Sr.No

Towers

Work Description

Progress 

1

1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM

Sub Structure Work

100%

2

AGANWADI, INTERNAL ROAD, GUARD ROOM  

 

100%

3

1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM, AGANWADI

Super Structure Work 

100%

4

INTERNAL ROAD

Super Structure Work 

85% 

5

GUARD ROOM  

Super Structure Work  

25%

6

1

Finishing Work 

90% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-100%)

7

2

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-100%)

8

3

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%)

9

4

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%)

10

5

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%)

11

6

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%)

12

7

Finishing Work 

95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%)

13

STP 

Finishing Work  

100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 25)

14

UGT

Finishing Work 

100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 100%)

15

AGANWADI

Finishing Work  

Tile work - 100%, Putty Work - 90%, Internal Primer Work-90%, External Primer-100%

16

COMMERCIAL - 1

Finishing Work  

50% (Tile work - 80%, Putty work - 75%, External Primer 80%)

17

VCB ROOM

Finishing Work  

75% (Flooring Work - 100%, Putty Work - 80%, External Primer - 100%)

18

ESS

Finishing Work  

95% (Flooring Work - 100%, Putty Work - 80%, External Primer - 100%)

19

INTERNAL ROAD

Finishing Work  

 

20

GUARD ROOM 

Finishing Work  

 

 

 