Sr.No
|
Towers
|
Work Description
|
Progress
|
1
|
1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM
|
Sub Structure Work
|
100%
|
2
|
AGANWADI, INTERNAL ROAD, GUARD ROOM
|
|
100%
|
3
|
1,2,3,4,5,6,7, UGT, STP, ESS, VCB ROOM, COMMERCIAL-1, METER ROOM & VCB ROOM, AGANWADI
|
Super Structure Work
|
100%
|
4
|
INTERNAL ROAD
|
Super Structure Work
|
85%
|
5
|
GUARD ROOM
|
Super Structure Work
|
25%
|
6
|
1
|
Finishing Work
|
90% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-100%)
|
7
|
2
|
Finishing Work
|
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-100%)
|
8
|
3
|
Finishing Work
|
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%)
|
9
|
4
|
Finishing Work
|
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-25%, External Primer-95%)
|
10
|
5
|
Finishing Work
|
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%)
|
11
|
6
|
Finishing Work
|
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%)
|
12
|
7
|
Finishing Work
|
95% (Tile work - 100%, Putty Work - 90%, Internal Primer Work-85%, External Primer-100%)
|
13
|
STP
|
Finishing Work
|
100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 25)
|
14
|
UGT
|
Finishing Work
|
100% (Railing fixing - 100%, Primer - 100%, Grating fixing - 100%)
|
15
|
AGANWADI
|
Finishing Work
|
Tile work - 100%, Putty Work - 90%, Internal Primer Work-90%, External Primer-100%
|
16
|
COMMERCIAL - 1
|
Finishing Work
|
50% (Tile work - 80%, Putty work - 75%, External Primer 80%)
|
17
|
VCB ROOM
|
Finishing Work
|
75% (Flooring Work - 100%, Putty Work - 80%, External Primer - 100%)
|
18
|
ESS
|
Finishing Work
|
95% (Flooring Work - 100%, Putty Work - 80%, External Primer - 100%)
|
19
|
INTERNAL ROAD
|
Finishing Work
|
|
20
|
GUARD ROOM
|
Finishing Work
|
|