Construction updates Sect-70A as on

Construction updates Sect-70A as on

We have completed super structure for tower no.1,2,3,4,5,6,7,8,9,10,11,12,14,15 & 16. In Tower No. 1,2,3 approx 86% of finishing work completed. Tower-10,11,12 & 15 approx 77% finish is done, In Tower no-4, 5, 6 & 7 approx 35% And in Tower no. 8,9,14 approx 40% finishing work is done. Lift installation in process for tower no. 1,2 & 3.