We have completed super structure for tower no.1,2,3,4,5,6,7,8,9,10,11,12,14,15. Tower-16 is on 9th floor where Shuttering work is in progress.  In Tower No. 1,2,3 approx 85% of finishing work completed. Tower-10,11,12 & 15 approx 75% finish is done, In Tower no-4, 5, 6 & 7 approx 30% And in Tower no. 8,9,14 approx 35% finishing work is done.