Construction updates Sect-70A as on

Construction updates Sect-70A as on

We have completed super structure for tower no.1,2,3,5,8,9,10,11,12,14,15. Tower no. 4 is on 9th floor, Tower-6 is on 12th floor & Tower-7 is on 9th Floor and Tower-16 is on 2nd floor where Shuttering work is in progress.  In Tower No. 1,2,3 approx 85% of finishing work completed. Tower-10,11,12 & 15 approx 70% finish is done And in Tower no. 8,9,14 approx 25% finishing work is done.