We have completed super structure for tower no.1,2,3,8,9,10,11,12,15. Tower no. 4 is on 3rd floor, Tower-14 is on 12th floor, Tower- 5 is on 8th floor, Tower-6 is on 6th floor & Tower-7 is on 3rd Floor and Tower-16 is on ground floor plinth work is in progress.  In Tower No. 1,2,3 approx 80% of finishing work completed. Tower-10,11,12 & 15 approx 60% finish is done.