Construction Update of Urban Homes-II, Sec-86

Construction Update of Urban Homes-II, Sec-86

Structure work in Tower-1,Tower-2, Tower-3, Tower-8, Tower-9 & Tower-10 is completed till terrace. Tower no.4 is on 5th floor, Tower no-05 is on 4th floor and Tower no.-06 is on 3rd Floor. Tower- 7 is on ground floor after completion of excavation, shear wall and plinth.